Jul 10, 2020
Upper Brookview Lane roofing work was completed (buildings 1-5 on the project map, below) and Lower Creekside Drive roofing work is in progress (buildings 6-12 on the project map). A couple of things to note: Due to the weight of their equipment for debris collection...
Jun 6, 2020
Roofing work began this past week on the upper Brookview Ln portion of this year’s project. Supplies were delivered to the area of the overflow parking lot next to 86 Brookview (half of the lot will remain available for parking). Roofers will generally work...
Aug 4, 2019
2019 Creekside Drive roofing complete! Roof shingle replacement work has been completed on all six of the upper Creekside Drive buildings that were due to be reroofed this year. To date, no plywood boards have required replacement. 2019 Brookside Lane roofs are up...
Jul 2, 2019
UPDATE: If you NO LONGER WANT your satellite dish to remain on your roof, contact Continental Property Management in advance of your roof replacement so the roofers will know it can be removed permanently. Reinstallation of Satellite dishes. If you have a Satellite...
Jun 29, 2019
Saturday roofing work. The Board has approved the roofing contractor’s request to work as many Saturdays as needed to supplement their Monday-Friday schedule. As most in attendance at our annual meeting agreed, if this helps get the roofs completed sooner,...
Jun 22, 2019
Roofing work began in earnest today, after rainy weather put a stop to yesterday’s plans. Here are a few important things we learned this morning: ⇒ Today’s work on the first building will be limited to the front half of the roof. Because the back yards...